Company Profile
Team
Business Verticals
The 3C Mandate
CSR
Group Companies
Clients
Platinum Rated Buildings
Gold Rated Buildings
Lotus Boulevard
Lotus Boulevard Espacia
Lotus Panache
Lotus Zing
Lotus 300
Lotus City
Greenopolis
Delhi One
Ozone Boulevard
Green Boulevard
Wipro Technologies
Patni Knowledge Center
Wipro Campus
Knowledge Boulevard
Tech Boulevard
Oxygen Boulevard (SEZ)
CSC Campus
I H D P
LVIS Noida
LVIS Gurgaon
Lotus 300
Overview
Floor Plans
Specifications
Layout Plan
Location
Club 300
Green Joys
Project Updates
E-Brochure
Residential
Lotus 300
Project Updates
2014
2015
2016
2017
2018
Jan.
Feb.
March
April
May
May IInd Updates
June
July
Aug.
Sept.
Oct.
Dec.
Project Updates for the month of May 2017
Basket ball court work in progress
DG set at site
Electrical panal installed
Electrical panel installed 02
kids play area work in progress
Pathway work in progress
STP work in progress 02
STP work in progress
Tower 1 and 2 external finishing in progress
Tower 1 apartment internal view 18th floor 02
Tower 1 apartment internal view 18th floor
Tower 1 apartment internal view 20th floor
Tower 1 apartment internal view 21st floor 02
Tower 1 apartment internal view 21st floor
Tower 1 apartment internal view 23rd floor
Tower 1 external paining work in progress 02
Tower 1 external paining work in progress
Tower 1 fire hose reel 21st floor
Tower 1 internal finishing view 13th floor 02
Tower 1 internal finishing view 14th floor 03
Tower 1 internal finishing view 16th floor 02
Tower 1 internal finishing view 16th floor
Tower 1 internal finishing view 13th floor 02
Tower 1 internal finishing view 14th floor
Tower 1 internal finishing work in progress 1st floor
Tower 1 internal finishing work in progress 3rd floor
Tower 1 internal finishing work in progress 5th floor 02
Tower 1 internal finishing work in progress 5th floor
Tower 1 internal finishing work in progress 7th floor 02
Tower 1 internal finishing work in progress 7th floor
Tower 1 internal finishing work in progress 8th floor 02
Tower 1 internal finishing work in progress 8th floor
Tower 1 internal finishing work in progress 12th floor 02
Tower 1 internal finishing work in progress 12th floor
Tower 1 kitchen finishing work in progress 1st floor
Tower 1 Kitchen view 18th floor
Tower 1 Kitchen view 23rd floor 02
Tower 1 Kitchen view 23rd floor
Tower 1 Lift lobby 23rd floor
Tower 1 lift lobby view 17th floor
Tower 1 lift lobby view 18th floor
Tower 1 main entrance work in progress
Tower 1 toilet finishing view 21st floor
Tower 1 Toilet view 20th floor
Tower 2 apartment internal view 26th floor
Tower 2 external repair work in progress
Tower 2 Internal finishing work in progress 13th floor 02
Tower 2 Internal finishing work in progress 13th floor
Tower 2 Internal finishing work in progress 25th floor
Tower 2 internal finishing work in progress 4th floor
Tower 2 internal finishing work in progress 5th floor 02
Tower 2 internal finishing work in progress 5th floor
Tower 2 Internal finishing work in progress 6th floor 02
Tower 2 Internal finishing work in progress 6th floor 03
Tower 2 Internal finishing work in progress 6th floor
Tower 2 Internal finishing work in progress 8th floor 02
Tower 2 Internal finishing work in progress 8th floor
Tower 2 Internal finishing work in progress 11th floor 02
Tower 2 Internal finishing work in progress 11th floor
Tower 2 internal finishing work in progress 15th floor
Tower 2 Internal finishing work in progress 17th floor
Tower 2 Internal finishing work in progress 19th floor 02
Tower 2 Internal finishing work in progress 19th floor
Tower 2 Internal finishing work in progress 21st floor 02
Tower 2 Internal finishing work in progress 21st floor
Tower 2 Internal finishing work in progress 24th floor
Tower 2 internal staricase view 26th floor
Tower 2 kitchen finishing work in progress 4th floor
Tower 2 Kitchen finishing work in progress 15th floor
Tower 2 Kitchen finishing work in progress 17th floor
Tower 2 Kitchen finishing work in progress 23rd floor
Tower 2 Kitchen finishing work in progress 24th floor
Tower 2 Kitchen view 26th floor
Tower 2 lift lobby finishing work in progress 4th floor
Tower 2 Lift lobby finishing work in progress 17th floor
Tower 2 Lift Lobby view 27th floor
Tower 2 Lobby finishing work in progress 23rd floor
Tower 2 Main entrance work in progress
Tower 2 toilet finishing work in progress 13th floor
Tower 2 Toilet finishing work in progress 15th floor
Tower 2 Toilet finishing work in progress 23rd floor
Tower 2 Toilet finishing work in progress 24th floor
Tower 2 Toilet finishing work in progress 26th floor
Tower 2 Toilet finishing work in progress 27th floor 02
Tower 2 Toilet finishing work in progress 27th floor 03
Tower 2 Toilet finishing work in progress 27th floor