Company Profile
Team
Business Verticals
The 3C Mandate
CSR
Group Companies
Clients
Platinum Rated Buildings
Gold Rated Buildings
Lotus Boulevard
Lotus Boulevard Espacia
Lotus Panache
Lotus Zing
Lotus 300
Lotus City
Greenopolis
Delhi One
Ozone Boulevard
Green Boulevard
Wipro Technologies
Patni Knowledge Center
Wipro Campus
Knowledge Boulevard
Tech Boulevard
Oxygen Boulevard (SEZ)
CSC Campus
I H D P
LVIS Noida
LVIS Gurgaon
Lotus Zing
Overview
Floor Plans
Specifications
Layout Plan
Location
The Leaf
Green Life
Project Updates
E-Brochure
Residential
Lotus Zing
Project Updates
2014
2015
2016
2017
2018
Feb.
March
May
Project Updates for the month of March 18
Lotus Zing Tower-6,exterior finishing work in progress.
Lotus Zing Tower-6,FHC installed.
Lotus Zing Tower-6,lifts panel work in progress.
Lotus Zing Tower-6,lobby work in progress.
Lotus Zing,Tower-5 electrical shaft finishing in progress.
Lotus Zing,Tower-5 external side portion finishing in progress.
Lotus Zing,Tower-5 FHC finishing in progress.
Lotus Zing,Tower-5 flat balcony finishing in progress.
Lotus Zing,Tower-5 flat bedroom finishing in progress.
Lotus Zing,Tower-5 flat living room portion finishing in progress.
Lotus Zing,Tower-5 flat washroom finishing in progress.
Lotus Zing,Tower-5 lifts finishing in progress.
Lotus Zing,Tower-5 lobby portion finishing in progress.
Lotus Zing,Tower-5 LV shaft finishing in progress.
Lotus Zing,Tower-5 Main stairs finishing in progress.
Lotus Zing,Tower-6 external side portion finishing in progress.
Lotus Zing,Tower-6 main entrance finishing in progress.
Lotus Zing,Tower-6 main stairs finishing in progress.